SMR data center deals

12 reactor design companies have announced agreements with hyperscalers or data-center operators. Kairos Power has Google (500 MW by 2035)↗, X-energy has Amazon (more than 5 GW by 2039)↗+, and Meta signed with both Oklo (1.2 GW in Ohio)↗++ and TerraPower (up to eight Natrium plants)↗+.

12 companiesChecked

Data-center deals
Rolls-Royce SMREquinix (via ULC-Energy)Rolls-Royce SMR4705Design review—Equinix signed a letter of intent with ULC-Energy, a Dutch nuclear developer planning Rolls-Royce SMRs, for a PPA of up to 250 MWe for its Dutch data centers (August 2025).2026-11-11
Westinghouse Electric CompanyData4AP300; eVinci3751Pre-licensing—Data4 selected the AP300 in March 2025 to evaluate deployment at one of its future European data centers (MoU).2026-11-11
TerraPowerMeta; Sabey Data CentersNatrium3452Construction licensed2,0302Meta agreement (2026-01-09) for up to eight Natrium plants: two new units plus rights to six more, up to 2.8 GW (4 GW with storage). Sabey Data Centers signed an MOU on Natrium deployment on 2025-01-21.2026-11-11
GE Vernova Hitachi Nuclear EnergyCrusoe (via Blue Energy)BWRX-3003002Construction licensed—Blue Energy signed a power agreement with Crusoe (November 2025) for an AI campus at Port of Victoria, Texas: gas power from 2028, nuclear by 2031. In August 2026 Blue Energy signed an engineering and licensing agreement with GE Vernova Hitachi for up to five BWRX-300s from 2032 to power a nearby data center.2026-11-11
StellariaEquinixStellarium; Alpha/Alvin experimental reactor2502Construction under review2,0352Equinix signed a 500 MWe pre-order (August 2025), then reserved the first energy from Stellaria’s inaugural 250 MW reactor (November 2025).2026-11-11
X-energyAmazonXe-100805Construction licensed—Amazon and X-energy plan more than 5 GW of Xe-100 projects in the US by 2039; the first, Energy Northwest’s Cascade facility in Washington, is planned at 960 MW from 12 reactors.2026-11-11
Kairos PowerGoogleKP-FHR; Hermes; Hermes 2751Construction licensed2,0304Google agreement (October 2024) for 500 MW by 2035. TVA PPA (2025-08-18) for up to 50 MW from Hermes 2 onto the grid that serves Google data centers, the first US utility PPA for a Gen IV reactor.2026-11-11
OkloMeta; Switch; EquinixAurora powerhouse751Pre-licensing2,0284Meta (2026-01-09): prepayment agreement for a 1.2 GW campus in Pike County, Ohio, first power as early as 2030. Switch (2024-12-18): non-binding 12 GW master power agreement through 2044. Equinix (2024-02-16): non-binding letter of intent for up to 500 MW, with a $25 million prepayment.2026-11-11
Deep FissionEndeavour (Edged)Deep Fission Gravity reactor (borehole PWR)152Pre-licensing2,0271Non-binding strategic partnership term sheet with Endeavour (2025-01-07) to co-develop 2 GW of nuclear capacity for Edged data centers; first reactors targeted for 2029.2026-11-11
NANO Nuclear EnergyTillman Digital Gateway; SupermicroKRONOS MMR154Construction under review—Non-binding framework with Tillman Digital Gateway (2026-08-24) targeting 2 GW by the mid-2030s and 6 GW by 2040, with up to $100M in milestone warrants; MOU with Supermicro on on-site reactors for AI data centers (2026-05-06).2026-11-11
Radiant IndustriesEquinixKaleidos14DOE test authorization2,0261Equinix pre-ordered 20 Kaleidos microreactors with deposits (announced 2025-08-14).2026-11-11
newcleoEvrocLFR-AS-30; LFR-AS-200—Design review—Non-binding MoU with Evroc and Studsvik to explore an SMR-powered data center at Nyköping, Sweden.2026-11-11

What these deals commit to

How the data is sourced

Offtake, options and pre-orders

The firmest deal here is a power purchase agreement on a named plant: TVA buys up to 50 MW from Kairos’s Hermes 2 for the grid that serves Google’s data centers↗. Meta’s Oklo agreement lets Meta prepay for power, which funds early fuel and site work↗++. Switch’s 12 GW with Oklo is a non-binding master power agreement↗++. Equinix signed a pre-order with deposits for 20 Radiant Kaleidos microreactors↗ and a 500 MWe pre-order with Stellaria, then reserved the first output of its 250 MWe reactor↗+.

Other data-center agreements

Deep Fission signed a non-binding term sheet to co-develop 2 GW for Endeavour’s Edged data centers↗, and NANO Nuclear signed a framework with Tillman Digital Gateway targeting 2 GW by the mid-2030s↗+.

Want the vendors closest to delivering? Cross-check this list with SMR construction permits and licences.